When a wholesale buyer needs a jewelry design that does not yet exist in our catalog, the clock starts earlier than most expect. At Hengdian (HD) Jewelry, custom development is built on brass with 18K gold plating at 0.1–0.3 micron and set with AAA cubic zirconia, and it follows a fixed production path: design confirmation, tooling (mold), plating, quality control, then packing and shipping. Because each step needs its own window, the practical rule is simple — open the custom conversation about two months before your target delivery date.
Ready-to-ship styles draw from a live catalog of more than 40,000 designs, so they can be ordered against stock at almost any time. A custom design does not exist until it is made, which means it must pass through tooling and plating before it can ship. That sequence — not the calendar date alone — sets the lead time. Planning two months out protects both your season and our production queue.
The annual production rhythm changes how early you must begin. Use this reverse-count as a guide:
| Your target window | Open the custom brief by | Why |
|---|---|---|
| Q4 holiday shelf (November) | Early September | September–November production is fully open; ready-to-ship dispatch runs 3–5 days, but custom still needs the full two-month path. |
| Spring / summer season (May–August) | About two months before | Outside the peak crunch, slots are easier to place, but the tooling-to-transit path is unchanged. |
| Valentine / New Year (February) | Late the prior year | February is the close of the custom plating season. After February, custom capacity is confirmed case by case against actual load — there is no fixed schedule. |
If your need is sooner than two months, the live catalog may already cover it. In-stock styles order at 6–12 pieces per style (HAI-coded hero styles at 36 pieces per style), each purchase order contains one design only, and 5–7 free samples are available per request with freight collected. Browse current stock through our ready-to-ship catalog before committing to a custom run.
Sometimes, if a slot is open and the design is simple, but it is not guaranteed. The two-month window is the reliable planning baseline; anything shorter depends on live capacity.
February is the close of the custom plating season. Open the brief in the prior year and confirm early; after February we confirm custom capacity case by case against actual production load.
No. Every order is QC-checked and dispatched from our Guangzhou facility in transparent OPP poly bags. There is no overseas warehouse in this model.
Send your references, target quantity, and target date through our inquiry channel, and we will reverse-count your start date and quote any tooling fee.
Custom development rewards early planning. Share your brief two months before the window and the production path above takes care of the rest — start your custom order plan with Hengdian (HD) Jewelry.